Saturday, February 9, 2013

A Nice Porch

On the scene.  The client contracted DammanWorks to build a new porch.  Design requests included a slightly larger deck, a bench to sit on and set items on when entering, and preferably no handrails.

Demolition day.  Old deteriorated aluminum flashing under threshold.

Rotten rim joist.



Old porch gone.  A clean slate.  Part of the project was to remove old siding and replace with Hardisiding.

Soft soil. Showing forms for two new footings.

Exposed mud sill.  Ready for new flashing before install of new deck sill/plate.

New deck sill through bolted to mud sill.  Drop girder in place for cantilevered deck joists. 


Decking being installed.  Note: a design solution was to drop the overall height of the deck to meet code restrictions for a deck with out handrails.

Stair stringers and treads installed.

Beginning of bench.




Stair detail.






Handrail fabricated and installed.  The footing the stairs are resting on is the height of the new grade.  Finishing touches will require bringing in a 1/2 yard of dirt and mulch.

Pre-grading but porch mostly complete.


Tuesday, January 8, 2013

Glass Block Tile Tub Surround

As was. Tile board surround. Not plumbed for a shower, double hung sash in the middle of it all.

Out it comes.

Reframing with new header.

framing done. installation of insulation.

exterior process picture

step back showing framing prior to insulation

Sizing for glass block


Drywall prior to tile board for extra R factor

Glass block and dry wall installed

Up goes tile board

and tile

while all this has been going on the shower line was roughed in.  more tiling.


Update on Summer Renovation

Butcher bloc counters cut and installed on existing cabintes.  Slab purchased from IKEA.




Alteration, extension of laundry built in cabintes.




Thursday, November 15, 2012

Northgate Bathroom Renovation

Old tub surround.  Plastic shell covering old tile and plaster board.  To be removed back to framing studs.

More complete view of bathroom before renovation, showing tile wainscot, outdated vanity and cam-mode, and tub surround.  All to be removed, including two layers of vinyl floor laid over un-salvageable pine tongue and groove.

Ppost demo showing framing wall studs and diagonal sub floor.  Area around cam-mode showing signs of old repairs and  water damage.  Has to be dealt with before proceeding.

View of damaged/missing sub-floor around cam-mode drain


beginning to remove damaged sub-floor

Meanwhile. Reconfiguring sink plumbing rough in as specified by requirements for new pedestal sink.

Back to sub-floor removal all the way past HVAC register

After repairing floor joists and blocking, new sub-floor is laid around cam-mode drain and HVAC register.  Prepped and ready for tile board installation

Old tub surround layers have been removed.  Prepped and ready for tile board installation.

This image showing post tile board installation and beginning of floor tile installation.  Also note: tile wainscot has been removed and new moisture resilient drywall has been installed in its place.


Tiling of tub surround has begun after installation of tile board.

Continuing with tile installation. Accent glass tile and soap dishes in their place.

Working the tile install around tub.

Detail shot of soap dish shoring while thinset mortar cures.


Dry fitting new pedestal sink.

Tile worked around to shower fixture side.  Also done in scope but not documented; plumbing rough in for new shower head height, mixer and hot and cold shut of valves added in plumbers alley.



Tile tub surround install almost complete, floor tile complete. Both floor and tub surround still need to be grouted. New drywall has been primed and received first coat of finish paint, beginning of base board and window apron trim install to match existing interior trim in rest of house.

New cam-mode installed.  Pedestal sink installed, just need to complete drywall and paint work behind sink.  Floor has been grouted, all walls and ceiling and trim have been prepped primed and received first coat of finish paint.

Showing new shower curtain rod and grouted tub surround.

Finishing touches like TP roll holder and towel bar installed.

Done

Done