before |
![]() |
before |
![]() |
before |
![]() |
before |
![]() |
before |
proposed drawing
proposed drawing
proposed drawing
![]() |
after hole was cut for new sliding glass door, found the mud sill below old door was termite riddled |
![]() |
had to take up deck boards to gain access to damaged sill |
![]() |
old cement slab stoop landing that deck was built over needed to be removed |
![]() |
exposed sill |
![]() |
cutting out the damaged sill |
![]() |
showing extensive damage |
![]() |
more demo |
![]() |
continued demo |
![]() |
once the damaged sill was cut out the floor joists, still in good shape, were exposed |
![]() |
temporary support in preparation for installation of new double 2x10 pressure treated sill |
![]() |
first 2x10 in place |
![]() |
2nd 2x10 in place |
![]() |
addition of deck plate and sistered deck joists |
![]() |
re-assembling deck |
![]() |
new sliding glass door in place |
![]() |
view of new door from dining room |
![]() |
view of door from deck |
![]() |
installed door ready for exterior trim |
![]() |
next stage in project. creation of pass through between kitchen and dining room |